The week of Jan. 11, crews will resume work on the retaining wall along the eastbound State Route 210 Base Line on-ramp, and work on the bridge columns and foundation at Highland Avenue bridge.

Bridge widening activities are underway at numerous locations throughout the project area, including Fifth Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange and Highland Avenue. Crews are working on the bridge widening at Base Line and Highland Avenue, where crews will work during daytime and nighttime hours. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.

During regularly scheduled night work this week crews will remove concrete forms from portions of the new retaining wall being constructed along eastbound SR-210 at Base Line. In consideration of the space and clearance required for various equipment being used to perform this work, the team has determined the following nightly full closures on eastbound SR-210 are needed:

Eastbound SR-210 closed between Base Line and Fifth Street: Nightly from 10 p.m. to 5 a.m., Tuesday, Jan. 12, through Thursday, Jan. 14 (into Friday morning). DETOUR: Exit eastbound SR-210 at Base Line and turn right at the end of the ramp, turn left on Palm Avenue, then left on Fifth Street to reenter eastbound SR-210.

SR-210 lane, connector and ramp closures

Ramp closures:

• Eastbound SR-210 on-ramp at Base Line -

• Nightly from 8 p.m. to 6 a.m., Monday, Jan. 11, through Thursday, Jan. 14 (into Friday morning)

• From 9 p.m. to Friday, Jan. 15, to 7 a.m. Saturday Jan. 16

• Westbound SR-210 on-ramp at Base Line -

• Nightly from 8 p.m. to 6 a.m., Monday, Jan. 11, through Thursday, Jan. 14 (into Friday morning)

• From 9 p.m. to Friday, Jan. 15, to 7 a.m. Saturday, Jan. 16

• Westbound SR-210 off-ramp at Base Line -

• Nightly from 8 p.m. to 6 a.m., Monday, Jan. 11, through Thursday, Jan. 14 (into Friday morning)

• From 9 p.m. to Friday, Jan. 15, to 7 a.m. Saturday, Jan.16

• Eastbound SR-210 off-ramp at Base Line -

• From 8 p.m. Thursday, Jan. 14, to 6 a.m. Friday, Jan. 15

• From 9 p.m. Friday, Jan. 15, to 7 a.m. Saturday, Jan. 16

Please note, nighttime lane/ramp closures may occur intermittently along eastbound and westbound SR-210, between Del Rosa Avenue and Interstate 10, Mondays through Fridays (into Saturday mornings), from 8 p.m. to 6 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR-210 as well as on local city streets.

Local street closures

Highland Avenue at SR-210 - Full closure between the eastbound SR-210 off-ramp and Arden Avenue, nightly from 9 p.m. to 6 a.m., Monday, Jan. 11, through Wednesday, Jan. 13 (into Thursday morning).

Arden Avenue at SR-210 - Lanes will be closed on Arden Avenue at SR-210, nightly from 9 p.m. to 6 a.m., Monday, Jan. 11, through Wednesday, Jan. 13 (into Thursday morning). At least one lane in each direction will remain open on Arden Avenue at SR-210 at all times.

About the project

The SR-210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR-210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the city of Highland, which will include widening three of the four interchange ramps. As the SR-210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between Fifth Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.

Please remember all construction is dynamic and the schedule is weather-permitting and subject to change.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.