The week of Oct. 4, crews will continue work on the retaining walls along the eastbound SR-210 Base Line on-ramp, perform concrete pours on SR-210 at Fifth Street, as well as slope paving work at Victoria Avenue and Pioneer Avenue, and continue constructing temporary bridge supports, also known as falsework, at Highland Avenue and Arden Avenue. The following nighttime closures of eastbound and westbound SR-210 are needed to facilitate this work:

Eastbound SR-210 closed at Del Rosa Avenue - Closed nightly from 11:59 p.m. to 5 a.m., Monday, Oct. 4 through Thursday, Oct. 7 (into Friday morning).

DETOUR: Exit westbound SR-210 at Highland Avenue and turn left at the end of the ramp, turn right on Arden Avenue, left on Lynwood Drive, and left on Del Rosa Avenue to reenter westbound SR-210 via the on-ramp.

Westbound SR-210 closed at Base Line - Closed overnight from 11:59 p.m. to 5 a.m., Monday, Oct. 4, and Tuesday, Oct. 5 (into Wednesday morning).

DETOUR: Exit westbound SR-210 at Base Line and turn right at the end of the ramp. Turn left on Boulder Avenue, right on Highland Avenue, and right on SB-330 on-ramp to reenter westbound SR-210.

Westbound SR-210 closed at Highland Avenue - Closed overnight from 11:59 p.m. to 5 a.m., Wednesday, Oct. 6, and Thursday, Oct. 7 (into Friday morning).

DETOUR: Exit westbound SR-210 at Highland Avenue and turn left at the end of the ramp, turn right on Arden Avenue, left on Lynwood Drive, and left on Del Rosa Avenue to reenter westbound SR-210 via the on-ramp.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including Fifth Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange and Highland Avenue.

SR-210 lane, connector and ramp closures

Connector Closures:

Southbound SR-330 Connector to eastbound SR-210

Closed nightly from 9 p.m. to 5 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Eastbound I-10 connector to westbound SR-210

Closed nightly from 9 p.m. to 5 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Westbound I-10 connector to westbound SR-210

Closed nightly from 9 p.m. to 5 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Eastbound SR-210 Connector to westbound I-10

Closed nightly from 9 p.m. to 5 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Eastbound SR-210 Connector to eastbound I-10

Closed nightly from 9 p.m. to 5 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Ramp closures:

Eastbound SR-210 on-ramp at Del Rosa Avenue

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Eastbound SR-210 off-ramp at Highland Avenue

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Thursday, Oct. 7 (into Friday morning).

Westbound SR-210 off-ramp at Del Rosa Avenue

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Westbound SR-210 on-ramp at Highland Avenue

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Thursday, Oct. 7 (into Friday morning).

Eastbound/westbound SR-210 off-ramps and eastbound on-ramp at Base Line

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning).

Westbound SR-210 on-ramp at Base Line

Nightly from 9 p.m. to 6 a.m., Monday, Oct. 4, through Saturday, Oct. 9 (into Sunday morning).

Please note, nighttime lane/ramp closures may occur intermittently along eastbound and westbound SR-210, between Del Rosa Avenue and I-10, Mondays through Saturdays (into Sunday mornings), from 8 p.m. to 6 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR-210 as well as on local city streets.

Local street closures

Base Line at SR-210 - Closed nightly from 10 p.m. to 6 a.m., Monday, Oct. 4, through Friday, Oct. 8 (into Saturday morning). Please note Base Line Street will not be closed at the same time as Fifth Street.

Fifth Street at SR-210 - Closed nightly from 10 p.m. to 6 a.m., Monday, Oct. 4 through Friday, Oct. 8 (into Saturday morning). Please note Fifth Street will not be closed at the same time as Base Line Street.

Sound walls and retaining walls

Crews are starting work to construct new sound walls and/or retaining walls throughout the project corridor. This work will take place Mondays through Saturdays during daytime hours (6 a.m. to 4 p.m.) and intermittently during nighttime hours (9 p.m. to 5 a.m.).

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.