The week of March 1, construction crews will continue work on the retaining walls along the eastbound SR-210 Base Line on-ramp and the westbound SR-210 on-ramp at Base Line, perform a concrete pour on SR-210 at Fifth Street and begin constructing temporary bridge supports, also known as falsework, at Highland Avenue and Arden Avenue. The following nighttime closures of eastbound and westbound SR-210 are needed to facilitate this work:

• Eastbound SR-210 closed from Fifth Street to San Bernardino Avenue: Closed nightly from 10 p.m. to 5 a.m., Tuesday, March 2, through Thursday, March 4 (into Friday morning). DETOUR: Exit eastbound SR-210 at Fifth Street and turn right at the end of the ramp, turn left on Alabama Street, then turn left on San Bernardino Avenue to reenter eastbound SR-210 via the on-ramp.

• Westbound SR-210 closed from San Bernardino Avenue to Fifth Street: Closed from 10 p.m. Thursday, March 4, to 5 a.m. Friday, March 5. DETOUR: Exit westbound SR-210 at San Bernardino Avenue and turn right at the end of the ramp, turn right on Alabama Street, then turn right on Fifth Street to reenter westbound SR-210 via the on-ramp.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including Fifth Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange and Highland Avenue. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.

SR-210 lane, connector and lane closures

Connector Closures:

Eastbound I-10 connector to westbound SR-210

• From 9 p.m. Thursday, March 4, to 5 a.m. Friday, March 5.

Ramp Closures:

Eastbound SR-210 on-ramp and off-ramp at Base Line -

• Nightly from 8 p.m. to 6 a.m., Monday, March 1, through Thursday, March 4 (into Friday morning).

• Nightly from 9 p.m. to 7 a.m., Friday, March 5, and Saturday, March 6 (into Sunday morning).

Westbound SR-210 on-ramp and off-ramp at Base Line -

• Nightly from 8 p.m. to 6 a.m., Monday, March 1, through Thursday, March 4 (into Friday morning).

• Nightly from 9 p.m. to 7 a.m., Friday, March 5, and Saturday, March 6 (into Sunday morning).

Eastbound SR-210 on-ramp at Fifth Street -

• Nightly from 8 p.m. to 6 a.m., Tuesday, March 2, through Thursday, March 4 (into Friday morning).

Westbound SR-210 on-ramp at San Bernardino Avenue -

• From 8 p.m. Thursday, March 4, to 6 a.m. Friday, March 5.

Please note, nighttime lane/ramp closures may occur intermittently along eastbound and westbound SR-210, between Del Rosa Avenue and I-10, Mondays through Saturdays (into Sunday mornings), from 8 p.m. to 6 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR-210 as well as on local city streets.

Local street closures

Highland Avenue at SR-210 - Full closure between the eastbound SR-210 off-ramp and Arden Avenue, nightly from 9 p.m. to 6 a.m., Monday, March 1, through Wednesday, March 3, (into Thursday morning) and from 9 p.m. to 11:59 p.m. on Thursday, March 4.

Arden Avenue at SR-210 - Lanes will be closed on Arden Avenue at SR-210, nightly from 9 p.m. to 6 a.m., Monday, March 1, through Wednesday, March 3, (into Thursday morning) and from 9 p.m. to 11:59 p.m. on Thursday, March 4. At least one lane in each direction will remain open on Arden Avenue at SR-210 at all times.

Fifth Street at SR-210 - Closed nightly, from 9 p.m. to 6 a.m., Monday, March 1, through Thursday, March 4, (into Friday morning) and from 10 p.m. Friday, March 5, to 6 a.m. Saturday, March 6.

Base Line Street at SR-210 - Crews will alternate closing one lane in each direction on Base Line Street at SR-210, nightly from 9 p.m. to 6 a.m., Monday, March 1, through Thursday, March 4 (into Friday morning). At least one lane in each direction will remain open at all times.

Full closure of Base Line Street at SR-210, from 10 p.m. Friday, March 5, to 6 a.m. Saturday, March 6.

Victoria Avenue at SR-210 - Crews will alternate closing one lane in each direction on Victoria Avenue at SR-210, nightly from 9 p.m. to 6 a.m., Monday, March 1, and Tuesday, March 2 (into Wednesday morning). At least one lane in each direction will remain open at all times.

About the project

The SR-210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR-210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the city of Highland, which will include widening three of the four interchange ramps. As the SR-210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between Fifth Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.